In order to have Work in Project, you need to create resources. Go to the resource sheet and add both resources. You will need to change the Project calendar as it is not 30 working days between April 1 and April 30. You will need to make every day a working day (to include Saturdays and...
So, without IDs - you want the task "break ground" to show the earliest of any of the break ground tasks in each country? This is not something natively accessible in Project. You could do some grouping but you'd have to code the "break ground" tasks using a spare field and then apply a...
Hi and welcome to the forum. I'm not sure I understand your question completely. Are the subtasks all grouped under the same summary task? Have you created a summary for each "country"? If so, the summary task start is the earliest start of any subtask and the summary task finish is the...
John is correct. If you give someone an mpp file, they can change any field, see all data. There is no version of Microsoft Project that allows for the locking of fields. Sorry.
I agree with John. Create the "Place order" task linked F to S with the "Receive parts" task. Add a lag of x days to show the shipping. You might also consider placing a deadline on the receive parts task equal to the date the product has been promised.
When you install Project 2013, it should ask if you wish to upgrade your global. If you wish to keep settings then you can upgrade versus a "clean" install.
Formulas cannot reference other task data. You can manually type the date into a spare date field and then calculate the difference there - but you cannot reference Task X finish date without using some coding.
Take a look at my reply to Grizz - second post in the thread. You'll need to select the option "Calculation for task and group summary rows" in the Custom Fields dialog window.
Does this happen with all files or just one? If just one - copy the view back from Global. File > Info, Organizer. If that doesn't work, it is possible your copy of global.mpt is corrupt. Exit Project. Find the copy of global.mpt in your user directory. Rename to GlobalOld.mpt and restart...
My guess is that there has been an interruption in the connection between your project file and the pool file through the WAN. If you open the files, make one assignment and save does it work? How stable is your WAN connection? Any slight interruption causes project (particularly older...
I'm afraid Project is really not designed that way. Overtime is specifically assigned per assignment - not per week - and each resource can only have one active cost rate and overtime rate per assignment. You can change cost rate tables per assignment and then assign that cost rate table in...
There is a subproject File field but it only shows data for the inserted summary line. Filtering on that would still leave the subtasks. I think the Flag field is easier to use.
I'm not following why a filter doesn't work. Drop in a Flag field and set the Flag on the tasks you wish to show to "yes". Then filter for only "yes". An autofilter should work just fine.