Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations strongm on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

How to set up different Overtime Rates

Status
Not open for further replies.

Hai Bang

Technical User
Aug 15, 2016
1
AU
Hello everyone

I need to set up different overtime pay rates for a resource. The overtime pay rate is 1.5x for the first two hours and double time thereafter.

For example, person A has standard rate of $100/hr (38 hours per week). This week he worked 45 hours, the payment should be $100x38 + $150x2 + $200x5 = $5100

Could you please help me to set up that?
Thanks in advance
Hai Bang
 
I'm afraid Project is really not designed that way. Overtime is specifically assigned per assignment - not per week - and each resource can only have one active cost rate and overtime rate per assignment. You can change cost rate tables per assignment and then assign that cost rate table in the task usage or resource usage view.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top