"Analyze Timescaled Data in Excel" is what you are after.
Dam nifty tool this, if you have 2000 you should already have it.
Love to take credit for this one, but alas...
Have a look at
thread913-643210
have a play with 'task type'.
if i understand your question
allocating more resource to a task with predictable hours should change the duration!
In principle
halve the resources - doubles the duration
double the resources - halves the duration
whether this physically can be achieved is another...
right!
if you need the task duration to stay as is - make the field 'task type' fixed duration.
I prefer to enter resources in a split view gantt chart and enter work rather than units.
that way total work will equal the project budget.
hth.
open "Calendar" view
double click on the view
select the tab "Date Shading"
then choose the calendar in the 'show working time for' drop list.