ShaColeman
Technical User
I have resources that start out a project with only .1 and .5 of time devoted to it. When I assign them to a task, whose duration but not work has been entered, the total work time for a task shrinks. Questions:
1. Should I enter work hours rather than duration and on what sheet?
2. Is the resource assignment dialogue box the only way to enter part time resources for the first 2 months that increase commitment over project life, or should I be using a resource calendar?
3. If I assign a resource to multiple tasks that can not be leveled, the program just assigns the % time available on resource dialogue box to all selected task, right? I actually have to do my own allocation of resource time by tasks in an interative method, right?
Thanks for help!!!
1. Should I enter work hours rather than duration and on what sheet?
2. Is the resource assignment dialogue box the only way to enter part time resources for the first 2 months that increase commitment over project life, or should I be using a resource calendar?
3. If I assign a resource to multiple tasks that can not be leveled, the program just assigns the % time available on resource dialogue box to all selected task, right? I actually have to do my own allocation of resource time by tasks in an interative method, right?
Thanks for help!!!