Ive developed a template in MSP 2003 which will be sent out to each of the PMs to uppdate their project tasks and progress into.
IS there a way in the future if required to send a new version of the template out to the PMs with changes and for them to be able to quickly transfter all the...
Problem
We have PMs updating excel reports with information in numerous cells in no particular order.
Rather than having the PMS update these excel reports and project plan templates I have been asked to investigate the following:
Can we provide links from the excel cells to go direct into the...
Question - i am in the practice of inserting less than 20 project plans into a programme plan in MS Project 2003 and producing a consolidated view.
IS is possible to insert up to 300 / 400 project plans into a MS Project 2003 plan blank template and filtering specific information without...
Hi
Ive set up a separate view with new table and filtering on numerous tags in one column.
When i look at this view and save the file then close it all looks good, But when i reopen the MS Project File the view and filter is not applied. Once i reapply the view all looks good.
IS there away...
When the work column is populated it can be displayed in hours or days.
To change the settings as a whole obviously i go to Tools \ Schedule \ Work is entered........and choosing the option of days or hours etc
A PM has asked me if Days are set in the overall settings as above is there a quick...
Can you please confirm that dependencies should not be set up on summary tasks as this can impact the critical path?
Is this correct that dependencies should be set up against individual tasks or milestones only and not summary tasks?
Can anyone please advbise if they use Earned Value in MS project and would they use it or not?
Reviewed some comments on Google but would like your opinion for implementing in an IT Organisation to project plans using no effort driven planning.
Thanks
Kaney
thanks for this information, have had a look through google and was interested in any fiurther views about managing thuis in MS Project.
Any further views appreciated?
Thanks
I have never used Earned Value in MS Project 2003 and have always managed tasks, milestones and non effort driven plans.
Can you please provide me your view of how practical and easy it is to implement and use Earned Value in MS Project Plans by various Project Managers with various experience...
Hi
Im using MS Project 2003, in a Programme plan im using the gannt details any slippage days calculated from the baseline finish and the finish. Unfortunately a project plan im inserting has used many different percentages assigned to the resources therefore when i insert into my programme...
Folks
Ive tried to set up a custom toolbar with my own buttons and macros assigned.
Ive then tried to copy it from the Global MSP to the individual project plan into Tool / organiser.
When i try and send the individual project plan file to others via email the toolbar doesnt send although the...
can i double check when the lag is set with e.g. 1'emon' can you please confirm this is 1 month.
Just want this confirmed as never used emon and why is it emon instead of 1mon????
thanks
im a regular user of this application but wondered what is the standard way of updating tasks that the experts use?
Do you
A -update by amending the finish date or
B - do you update by increasing duration
I know by doing A amends the task constraint although
What do the experts prefer to...