It might be easier than you think. If working with an MPP file Save As an Access File. Go into access & open the file there. You can create relationships, add tables, etc. You will probably be working with the Table MSP_Tasks. You can then open the file in either access or project...
Hi Janice
Your question is from March but we have a similar problem. First Project automatically converts things to milestones (duration = 0 but Start/Finish Dates OK). Then it splits the task. To test, we cleared out all resources, and actual data (Edit, Clear, All for Actual Start, Finish...