Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations SkipVought on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. procygnus

    How to Change Highlight Color of Holidays

    asta powerproject apparently gives you the ability to color each bar according to nature of task!
  2. procygnus

    Allocating resources by percentage

    Tony - the question is whether it is possible to do what you ask using MSP? Nope. Resource loading in MSP is static, ie, you specify the workload or adjust the calendar and other assignment settings to reflect a balanced workload. What you are asking for is called finite scheduling. Here is a...
  3. procygnus

    How to Change Highlight Color of Holidays

    wrbird - nope! holidays are just more 'non-working hours'. other than aesthetic appeal, it wouldn't matter, would it?
  4. procygnus

    % Work Complete

    Pedro What is your update cycle? Daily/Weekly? What is your update procedure? A few observations: 1. I see you use choose to display progress line at current date in relation to actual plan. Assuming your update cycle is one week, it is more prudent to display progress line at project status...
  5. procygnus

    How to Change Highlight Color of Holidays

    On the timescale, right click and select 'Timescale'. Select tab 'Non-working time'. Choose appropriate color and pattern from drop-down list.
  6. procygnus

    % Work Complete

    Pjadss - can you share your project plan?
  7. procygnus

    Allocating resources by percentage

    The statement - "I want to associate task A with the 20% load" - offers the solution. Have you tried assigning a separate Task Calendar for Task A?
  8. procygnus

    Can outsourcing project support help?

    Stuman - its applicable for any type of work. IT services received all the hype (and flak). At the low end of the spectrum (in terms of pricing - $10-25 per h) you have medical transcription, math tuitions and inbound call processing and such stuff. The mid-tier ($40-150 per hour) comprises IT...
  9. procygnus

    Consulting rates in Thailand

    Anyone here has any knowledge of US$ consulting rates chargeable by contract systems integration consultants (architects, systems analysts) in Thailand?
  10. procygnus

    My Critical path is not complete

    Ok - so the June 11 problem persists and cannot be replicated in my installation. Try this little exercise: 1. Open a new project. 2. Open Tools/Change Working Time 3. Create a new definition for workweek for 11-18 June. Start by selecting the range of dates in the calendar displayed. 4...
  11. procygnus

    Allocating resources by percentage

    By 20%, I assume you want this resource working 20%*8=1.6h per day through April, ie, 1h 36 minutes a day. Since this arrangement is for April alone, the answer lies in the resource calendar for this April part-timer. See plan attached for (a) full-timer and (b) part-timer. Both work 408h. But...
  12. procygnus

    Can outsourcing project support help?

    Stuman - its obviously working quite well considering that at $150 billion+ it constitutes some of the fastest growing sectors of the economy in developing countries. If the offshore team is well integrated, and the hand-off of processes well managed, your teams productivity can be increased...
  13. procygnus

    My Critical path is not complete

    All constraints have been removed - that's great! But you had a deadline of Mon 08-08-11 23:00 on summary task 1 (MSC SUBSEA ENGINEERING DISSERTATION). Remove it and you have a critical path starting at Task 36 (Introduce a girth weld into the plain pipe model and run the analysis again for all...
  14. procygnus

    Release 8??

    Why has this forum not seen any activity since Dec 2010? Still figuring Release 8? Is Oracle headed in the right direction?
  15. procygnus

    My Critical path is not complete

    Task 38 - "Generate and record the observed behaviour of simulated pipe for each pipe specification" - appears to have 22h of work that needs to be done between 1200h on Sat 11/6 to 1200h on Tue, 14/6. However for some reason 11 June has default timings [0900-1300; 2200-2300] or 5h workday even...
  16. procygnus

    Resource allocation

    And uncheck "Effort Driven"!
  17. procygnus

    Auto assign a resource from a group during leveling

    You will need a finite scheduling software package - not a plain old project management package like MSP.
  18. procygnus

    MSProject 07 - No Server - RISK

    Just a suggestion: Qualitative risk can be listed as notes to a dummy activity. Quantitative risks have impact - cost or schedule. So, you could consider using Activity and Resource (Work/Material/Cost) assigned to such 'risk activities' to build your budgeted risk contingency.
  19. procygnus

    Free Slack Question

    Nigel - there appear to be many common beginner errors in your plan that you may like to rectify in discussion with a mentor. I will list some below as it comes to my head: 1 Calendar: you are using the standard calendar with default work hours 2 Task Duration - you have fractional durations...
  20. procygnus

    My Critical path is not complete

    Check the first task on critical path for constraints and clear it!

Part and Inventory Search

Back
Top