I'm sure this is a basic question but if I have weekly recurring project meetings with x number of resource attending each meeting, and that meeting task duration is 1 hour how do I get prject to allocate one billable hourly rate for each attending resource?

Currently it is dividing up the one hour by number of resources assigned.

thanks.
 
Assign billing rates to the resources.

View > Resource sheet ... you'll see the appropriate columns.
 