Hi,
I have about 80 resources in my Project plan.
I want to create 'Who does what when' report showing only 14 out of 80 resources.
How can I get rid of unwanted resources while creating this report.
Click on the minus sign at the start of the Resource name if you want to hide that person's tasks in the report; click on the plus sign if you want to show the resource's tasks in the report.
Run the report.
In the report you will still see a single line with just the resource's name even if you have hidden the tasks for that resource.
1. Prepare the data
View | Resource Sheet
Display the Group column
Put something unique in just the resources you want on the report - I entered "PDQ"
2. View the report
View | Reports | Assignments ...
Single click on "Who does what when"
Click Edit
Click on the Definition tab
Change the Filter to "Group ..."
Click OK
Click Select
Enter the Resource Group from step 1: PDQ
Click OK