Hello:
I am a general contractor. Our typical schedule has several sections i.e. Pre construction, Submitals, Procurement, Site work, Foundations, Building shell, Finishes. After the Subcontracts are awarded, each Subcontractor is set up as a resource.
Each Sub will have activities in several sections, for example, ABC Electrical Contractors, under submittals, procurement, site work, Building shell and finishes.
I want to sort the schedule so that Each sub can see the dates and activities they are required to perform on the project. So under ABC electrical we would see:
ABC Electric submit fixtures 1/1/11 to 1/15/2011
ABC Electric order Fixtures 1/15/11 to 3/5/2011
ABC Electric install site underground 4/10/11 to 4/18/11
ABC Electric install building rough in 3/15/11 to 6/21/11
ABC Electric install fixtures and trim 9/10/11 to 10/21/11
using sort> resource name; only sorts under each project sub section.
I want to produce a report that shows the expected dates that ABC electric and all other subs will be required on the project. This was a snap in early versions but I can't figure it out in 2003.
Please help
I am a general contractor. Our typical schedule has several sections i.e. Pre construction, Submitals, Procurement, Site work, Foundations, Building shell, Finishes. After the Subcontracts are awarded, each Subcontractor is set up as a resource.
Each Sub will have activities in several sections, for example, ABC Electrical Contractors, under submittals, procurement, site work, Building shell and finishes.
I want to sort the schedule so that Each sub can see the dates and activities they are required to perform on the project. So under ABC electrical we would see:
ABC Electric submit fixtures 1/1/11 to 1/15/2011
ABC Electric order Fixtures 1/15/11 to 3/5/2011
ABC Electric install site underground 4/10/11 to 4/18/11
ABC Electric install building rough in 3/15/11 to 6/21/11
ABC Electric install fixtures and trim 9/10/11 to 10/21/11
using sort> resource name; only sorts under each project sub section.
I want to produce a report that shows the expected dates that ABC electric and all other subs will be required on the project. This was a snap in early versions but I can't figure it out in 2003.
Please help