hey all
never set up redundancy and fallback. reading the docs i have a few questions maybe someone can help
scenario
site A, IP500v2, 100 ip phones, vmpro (basic ivr 12 port), ccr
site B 40 ip phones
Site B is going to be a DR site but still used daily.
IP500v2, backup vmpro, ccr???
All IP phones across both sites are going to register to site A.
If Site A IP500 fails I can have IP phones switch to SiteB after 3 minutes. I don't need endpoint licenses for each IP phone. But do I need SCN channel licenses for each concurrent call or does simply setting the SCN trunk as Fallback work with no limits?
If Site A VMPro fails, Site B backup vmpro becomes operational. what licensing do I need on the backup vmpro? 12 ports again?
If Site A IP500 fails, can CCR (site A) report on site B IP500 calls? Or can I have a CCR install in SiteB only reporting in these scenarios? As in there will be no calls on SiteB unless SiteA is down.
In a fallback scenario what happens with Hunt Groups, I have CCR groups, so would I backup groups or just recreate them on the backup IP500?
What else should I watch out for??
thanks in advance
never set up redundancy and fallback. reading the docs i have a few questions maybe someone can help
scenario
site A, IP500v2, 100 ip phones, vmpro (basic ivr 12 port), ccr
site B 40 ip phones
Site B is going to be a DR site but still used daily.
IP500v2, backup vmpro, ccr???
All IP phones across both sites are going to register to site A.
If Site A IP500 fails I can have IP phones switch to SiteB after 3 minutes. I don't need endpoint licenses for each IP phone. But do I need SCN channel licenses for each concurrent call or does simply setting the SCN trunk as Fallback work with no limits?
If Site A VMPro fails, Site B backup vmpro becomes operational. what licensing do I need on the backup vmpro? 12 ports again?
If Site A IP500 fails, can CCR (site A) report on site B IP500 calls? Or can I have a CCR install in SiteB only reporting in these scenarios? As in there will be no calls on SiteB unless SiteA is down.
In a fallback scenario what happens with Hunt Groups, I have CCR groups, so would I backup groups or just recreate them on the backup IP500?
What else should I watch out for??
thanks in advance