I have used Project for a while but usually in very simplistic projects. Here is my problem.
I have a very detailed project tracking the project to the hour. There are 16 hour work days (Mon-Sat) consisting of 2 8-hour shifts that do not overlap (6A-2P & 3P-11P). The resource calendars show 8-hours per day for the workers. There are separate calendars for 1st shift (6A-2P) and 2nd shift (3P-11P) resources.
When I have a 20 hr task with one 1st shift resource and one 2nd shift resource assigned, Project allocates the resources as follows: 8 hr per worker (both) for the first day and 2 hours per worker (both) for the second day.
What I want it to do is schedule each worker 8 hours the first day and the final 4 hours of the task to the 1st shift worker in the second day so that the task is completed as soon as possible.
What am I doing wrong? Can Project do this? Any suggestions are greatly appreciated.
Thanks.
I have a very detailed project tracking the project to the hour. There are 16 hour work days (Mon-Sat) consisting of 2 8-hour shifts that do not overlap (6A-2P & 3P-11P). The resource calendars show 8-hours per day for the workers. There are separate calendars for 1st shift (6A-2P) and 2nd shift (3P-11P) resources.
When I have a 20 hr task with one 1st shift resource and one 2nd shift resource assigned, Project allocates the resources as follows: 8 hr per worker (both) for the first day and 2 hours per worker (both) for the second day.
What I want it to do is schedule each worker 8 hours the first day and the final 4 hours of the task to the 1st shift worker in the second day so that the task is completed as soon as possible.
What am I doing wrong? Can Project do this? Any suggestions are greatly appreciated.
Thanks.