I have a 81 and 11 tied together with Tie lines and am confused about clocking between the two. Do I need a clock controller in the 11 and what do I set up in the DDB as far as clocking for the 11? I need the 11 to clock off the 81.
Thanks for the help
I changed out the Clock controller and when I do ssck 0 I get a DTI061 and Tracking ERR I can put into FRUN and I get no errors. When I bring up loop on the 81 I get a DCH relaese No Response.Loop on 81 is 21 loop on 11 is 1
myarberry...you said you are getting dch release are
you programmed as a plain t1 not a pri which has a
d-channel.are you going thru a telco or going thru
your own cable plant.if a local telco is involved
how is it provisioned.
I am using a Cross Over cable I know that the Clock is enabled. When tracking on Primary CC light flashes,When I put in Free Run CC light steady but D channels start to go up and down.