I would like to know if it is possible to automatically calculate a task's duration based on the duration of a predecessing task?
For example, if Task 1 takes 20 days to complete, and Task 2 takes half as long to complete as Task 1, I would like MS Project to automatically calculate Task 2's duration to 10 days (50% of Task 1). Is this possible? I am using MS Project 2003.