Which version of Project are you using? And do you mean that you want to customize one of the pre-defined standard reports or do you want to customize one of the pre-defined Visual reports? (I'm guessing that you want to change one of the standard reports and I'm hoping that it isn't one of...
You're actually asking two questions here.
1. Create the task
Make sure the following columns are displayed: Duration, Work, Resource Names, Type.
If you have a resource assigned, delete the resource.
In the Work column enter: 2 hours
In the Duration column enter: 3 days
In the Resource...
In a nutshell, departments propose projects to the Projects group.
Projects are then defined as mandatory (usually to meet changed legal requirements) and optional. The optional projects undergo a cost benefit analysis and the results are compared to a hurdle rate and those that pass under...
@Julie
I've been reading a number of your posts in various threads. You have been giving consistently excellent advice ... you're a real asset here.
In this particular thread, I thought your comment about a "rolling wave" was an especially subtle understanding of the environment in which the...
You'll need VBA to do that.
But ... here's a workaround that sorta works:
1. Set Start1 so it equals Start
2. Set Finish1 to it equals Start + Duration + Number1
Now set your Gantt Chart to use Start1 and Finish1 when drawing the Gantt lines.
I say "sorta" because when you use predecessors...
@Julie ... I'm pretty sure it has to do with the date formats. If he's using (as I do) "ddd mmm d, yy" ("Fri Apr 6, 12") then it gets copy-pasted as a text field; if he uses "mm/dd/yy" (4/6/12) then it gets copy-pasted as a date field -- there may be other formats that copy-paste as dates, I...
In P2010
Open the file
Click on File > Options
In the new display click on "General"
On the right locate "Date format" and select the second one ("1/28/09") Note: This is a global setting and all other projects will open with their dates in this format.
Click on OK
Copy&paste from P2010 date...
Open the file and display the Gantt Chart view
If it isn't already on, turn on AutoFilter.
If it isn't already displayed, display Resource Names column
Create a new filter
Click on View > the filter drop down > New filter
In the popup:
Name: PDQBach
Show in menu: check mark...
So, using my example above, you want something like this (with the ID as the first data element and the task name as the second data element in each row):
ID Task Name
==== =========
2000 A
2100 B
2110 C
2120 D
2200 E
2210 F
3000 G
Ain't gonna happen.
The ID field is dynamic...
What is CSI numbering?
Could you give us an example of what MSProj does and then the same tasks with your desired approach. You could probably get away with simply calling the tasks A, B, C, etc.. (no need for great detail) the IDs would, for MSProj, be 1, 2, 3, etc., and the successors (no...
How about renaming the file extension from .mpp to .dat and sending that file.
Or put the file into a zip file and changing the extension on that file to .dat
In either case, when the client gets the file, change the extension back to the correct one.
If that doesn't work, try deleting all...
I almost always need to get both simply because it is an exceptionally rare occasion where someone works exclusively on a deliverable for a given period of time (and, therefore, duration and work are the same).
I need work so I determine the project cost (work * fully encumbered resource cost)...
This is *not* the way I would go about managing the project. C. Northcote Parkinson's first law of economics is is particularly germane here.
In fact, your approach is so unacceptable that Project (which allows you to do so much) doesn't have the built-in functionality to let you do that...