Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations strongm on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Can anyone tell me how to do this?

Status
Not open for further replies.

btroupjr

Technical User
Nov 14, 2012
2
US
I need to be able to assign a resource 2 hours work, but allow him a duration of 3 days to complete the task in the project.
This way I can still track the actual work hours assigned, versus the duration of the task. Any help is appreciated.
 
You're actually asking two questions here.

1. Create the task
Make sure the following columns are displayed: Duration, Work, Resource Names, Type.
If you have a resource assigned, delete the resource.
In the Work column enter: 2 hours
In the Duration column enter: 3 days
In the Resource column enter: the resource name.
In the Type column select: Fixed Work <<-- this is important.


2. Enter actual work
Here's where life gets interesting. You see, there are several possibilities for entering actual work. You can actually enter it in on a day-by-day basis but if the task isn't complete within the original Duration, what do you want to do? Do you want Project to recalculate the duration or do you want to establish a new duration yourself?

Or, perhaps, the resource actual hours match the originally estimated work hours but, in fact, it will take more work hours and more duration to finish the task.

Or you can enter the actual hours worked in the Actual Work column. But, again, what happens when you enter an Actual Work amount that matches the originally estimated Work but the deliverable still isn't finished?

Frankly, it seems to me that you are still in the early stages of learning about MSProject so it would be best for you to concentrate on actually getting the deliverables produced than it would be to focus on actual hours (compared to the estimated hours). If I were you I would use the column %Work Complete (*NOT* %Complete) and track progress that way.

So ...
create each task with 10 hours of Work no matter how much work is really involved. (So, ignore your 2 hours of work mentioned above)
set the Duration to the expected elapsed time. (So set it to 3 days for this task.)
assign the Resource.

Then, as often as you feel necessary, get back to the Resource and get the %Work Complete (how far along are you?) and get the revised Finish date.

In fact, it's still more complicated than that because entering a specific Start or a specific Finish date creates an automatic constraint on the task. But we'll save that for the future.
 
Hello PDQBach,

Thank you very much for your assistance. I appreciate it very much.

I am a moderately experienced user, but I suffer from the occassional brain fart some days. Your articulate and detailed explaination has reminded me of exactly what I needed to do.

I understand exactly what you are saying, and the issues revolving around managing a project via actual work vs. Durations. I will continue to manage my projects via task durations, as I find it much easier to do as well as it provides me with the sufficient level of resolution.

The request for the actual work assigned inside the task duration was a request from my executive team so that they can visualize actual resource usage, and foresee department workload on a finer resolution than I could normally provide. This is a case where historical data provided would not be adequate due to recent structural/departmental changes and would not be accurate enough to predict future resource requirements going forward.

Folling the steps you provided will help me accomplish exactly what I need to do. Thanks again for your help and insite.
 
> I will continue to manage my projects via task durations

And I will sleep soundly tonight knowing that your projects are in good hands!
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top