Hi Julie,
I created a new Master Project and performed the following steps.
1. Inserted the 1st project
2. Created the Visual Report (Assignment Usage) as indicated earlier in my post - No error message.
3. Inserted the 2nd project
4. Repeated Step 2 - No error message.
5. Inserted the 3rd...
I am using MS Project 2007 SP2. Is there an SP3 available?
I have inserted 5 projects into the Master Plan and each of these are stored in different paths on the server. I have the Master Project Plan on my desktop.
O.k I will try to create a Master Plan, by adding 1 project at a time.
thanks...
Hi Julie,
I don't get the error message when building the visual report for a single project plan. I just now tried once again from the Master Project Plan, but got the same error message. Is the error because i selected " Link to project" when inserting the individual plan into the Master...
Hi Julie,
Thanks for the info.
Hi Malforso,
I tend agree with you, as i have never linked between projects and don't want to disrupt MPP, else it would be tediuos to undo everything. Currently, i am looking as the Resource Usgae View to check if any resource is overallocated, but i am not...
Hi Julie & Malforso,
The objective is to know as to when a work resource is available so that a next task can be assigned. This is across multiple projects that i am able to track through the Master Project Plan. I thought that the timescale table (right-hand side table view) in the Resource...
Hi,
I am using MS Project 2007 and trying to create a visual report. I get an error message
" An unknown error has occurred.
An error occurred and the requested action could not be completed at this time."
when project is " Building local OLAP cubes...". I performed the following steps.
1...
Hi,
I am using a Master Project Plan and would like to know how to generate a graphical report (visual report) of the timescale table, in the Resource Usage view.
I am unable to attached the sample of a graphical report that i would like to acheive.
thanks
Robert
Hi Julie,
Yes, it is the same resource across the 3 projects. Since i have already started tracking these projects, where in 1 of them, the project is roughly 60% complete; do you think at this point it would be "easy" to create a common resource pool (without disrupting the plan)? or would it...
Hi,
I am using MS Project 2007 standrard version for planning and tracking the projects.
Currently i am tasked to handle 3 critical projects at the same time. The resources for these projects are more-or-less the same.
Today, i am trying to use the Master Project Plan option, but have a few...