Thanks for your help all:
I have it figured out.
Using the resource usage view I inserted the Start and Finish Columns, by right clicking, the column heading area,selecting insert column and selecting "start" and "Finish". I then right clicked on the "Detail Styles" portion of the page (page...
Lill:
The resource usage view, at least on my computer, does not provide the start and finsh dates for eash activity, but rather a day by day listing of work projected out to infinity.
Sub contractor's eyes glaze over when presented with a 300 item schedule. I want to provide them a view that...
Thanks for the reply, Julie. I tried both of these before I posted and they don't yield the results I am looking for. The results I was able to get in the past laid things out just like they appear in the Task View, but all the tasks are grouped by resource.
With out programing changes, sticking with the limits of the program as it comes out of the box, I don't think you can do this because the program operates in real time.
Try entering a milestone activity (an activity with 0 duration)
"END OF YEAR ONE" on the date of the 1st aniversery of the...
Hello:
I am a general contractor. Our typical schedule has several sections i.e. Pre construction, Submitals, Procurement, Site work, Foundations, Building shell, Finishes. After the Subcontracts are awarded, each Subcontractor is set up as a resource.
Each Sub will have activities in several...