Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations strongm on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. ProjectMonkey

    Product vs Process WBS for performance measurements

    I prefer not to constrain the WBS by trying to make it fit a product(prince 2) approach or process based approach. Just ask what needs to be done and build the WBS from there. T Morphy MS Project tips http://www.stakeholdermap.com/ms-project/ms-project.html
  2. ProjectMonkey

    best practise on pausing a project in Microsoft Project 2013

    Save a baseline of the project. Then add actual start and actual finish dates to the task table. Finally add an indicator for the current date to the gantt view. Now MS Project will show the slippage against the baseline. Hope that helps. T Morphy MS Project tips...
  3. ProjectMonkey

    Automatically chaning dates

    Hi Ed, Have you tried putting a finish to start dependency between the tasks? Look for the predecessor column in the task table and put task 1 as a predecessor to task 2. Make sure that task 2 is set to start 'As soon as possible'. Click the advanced tab in the task information box to check...
  4. ProjectMonkey

    Project Mangement Training

    I agree with john. In the UK you might also consider Prince 2. http://www.prince-officialsite.com/ T Morphy http://www.stakeholdermap.com/project-templates/ms-project-templates.html
  5. ProjectMonkey

    Task & Resource Columns

    Project 2007 introduced two types of assignment extra fields - those visible in the Task Usage view (Task Assignment fields) and those visible in the Resource Usage view (Resource Assignment fields), and they are completely different. See...
  6. ProjectMonkey

    Date Change Alert Multiple Tasks

    If you put a 'must start on constraint' on the milestones MS project will warn you if a change to a predecessor task will create a scheduling conflict. However, I wouldn't recommend setting too many constraints in your plan. T Morphy http://www.stakeholdermap.com/plan-project/plan-project.html
  7. ProjectMonkey

    Insert text to date field

    Add resource names to the resource column and filter on resources so that management can see what they feel is applicable. There are lots of ways around this and MSP has many reports you can use. Why are they so set on the date field? I am pretty sure you can't add text and I don't know why...
  8. ProjectMonkey

    resource use and work calculate

    What software are using and can you send your plan or an example showing want to achieve? T Morphy http://www.stakeholdermap.com/plan-project.html
  9. ProjectMonkey

    How to tell Project a 3-hour tasks will be done in 3 days?

    Regarding setting a task to begin on a particular date. PDQBach is right that you can simply enter the start date, but I also don't like setting start dates because it can have some important impacts on the critical path. 1. MS project may break links to the task in order to allow the fixed...
  10. ProjectMonkey

    project management courses

    I agree, PMI is a very good qualification and is recognised worldwide. If you are UK based you may also want to consider APMP. This is qualification provided by the Association of Project Management based in the UK. If you want to work in the public sector in the UK it is also worth getting...
  11. ProjectMonkey

    I need help with project managment

    Looks like you have some good responses to your question. One thing I am not clear on - are you interested in product development or software implementation? If you need an example for software implementation you can find one at: http://www.planproject.co.uk/templates.html Bear in mind that...

Part and Inventory Search

Back
Top