I have a number of milestones (30-40) which can not be moved in terms of the finish date. Is there a method of raising an alert if one of these milestones finsih dates gets moved due to a dependantcy ?
If you put a 'must start on constraint' on the milestones MS project will warn you if a change to a predecessor task will create a scheduling conflict.
However, I wouldn't recommend setting too many constraints in your plan.
An alternative to constraints are Deadlines. Double click on the task and set a deadline date. If your tasks slide past the deadline date, the indicator column will show a red alert.
Insert the deadline date field into the task sheet to make the insertion of the same deadline date easier.