Hi,
we use XPI: and XPO: for incoming and outgoing interfaces.
We want to color only the NAME column RED when 'XPI:'-string is taken in the NAME field (starts with XPI:).
We want to color only the NAME column GREEN when 'XPO:'-string is taken in the NAME field (starts with XPO:).
I read a...
We have another issue wrt the now usage in formulas/filters:
Required:
"Filter that includes task with finish date less than or equal to today"
Initial thought for filter:
IIf([Finish]<=Now(),True,False).
But this doesn't work. It will not mark tasks 'True' which end on the same day as...
Well, after some checks on other laptops it seemed that my macro security setting was too high which prevented the macro execution.......
Thanks!
Topic can be closed.
We have defined a standard format box set-up for the figures in the network diagram so that all network diagrams will look the same.
We now want to use the general style settings for tasks/milestones/summaries (critical and non-critical) to be applied for all users.
Users however have already...
PDQBach, thanks for the advice and your patience but I think I'm still doing something wrong or I don't understand.
Yes the filter is available after saving MSP and I did put the 2 pieces of programming in the proper place.
However, when I change the date of the computer to see if the now...
Yes the filter is working properly and it's visible when the macro is activated manually.
However, I want to have this filter loaded at MS Project start-up time without activating a macro manually. So automatic execution of this macro so that the filter is available for use.
The issue is that I...
Thanks PDQBach.
This looks like the solution.
A macro for that specific filter works fine. The only issue I have is that the macro needs to be initiated once before you can use the filter.
Is there an automatic macro execution within MSP2007 at start up time without pressing any keys? That...
I want to use the todays date in a filter.
How can I do that?
Apparently there is no field in the filter function that can be used as todays date without translating it to the date of today. That means that tomorrow the yesterdays date is set in the filter. The objective is to run the filter...
When the standard calendar is replaced by a new calendar on task level an icon appears in the indicator column to display the calendar overwrite.
When that calendar is replaced later on by the standard calendar again, the icon will not disappear. Is there a possibility to remove the icon in the...
In SP1 (which we have installed) I see the solved issue: When you open a project in Microsoft Office Project 2007, you find that all custom field data is missing.
In SP2 I don't see any solved issue wrt this topic.
I have only a renamed textfield and the (text) data is lost. Reading the...
e.g. text1 which we use internally for the owner of a deliverable/task. We have renamed the text1 field therefore as 'Owner' in MSP2000. I'm not sure whether that has anything to do with it.
Hi,
reading the forum I noticed that this issue was reported but no solution was presented. We have SP1 installed.
What can be done about it?
I guess that it appears when the MPP file is opened with MSP2007 and saved as MSP2000.
Advice is appreciated