Two more question on this.
If I have the availability 90% for a resource.
She/he will spend 50% in Project A and 40% in project B.
Question 1) if the resource needs to spend 60% in June on project A. How do I solve that in an easy way? Same way if the time is less? For example 40% for project A...
Hi Again
I have many resources in my project and have to report availability per person.
If I have person A always working 50% but person B is only working 40% until a specific date. How do I enter person B's specific "request"? At the moment they look availible.
Is it also possible to have one...
Hi
I have one file for resources and 2 files for projects.
They are connected.
When I updated the resources vacation the end date in the project files changed.
Settings are:
Fixed duration
Not effort driven
What I want the MS to do:
The end date should never change
If 2 resources is working...