Hi
I have one file for resources and 2 files for projects.
They are connected.
When I updated the resources vacation the end date in the project files changed.
Settings are:
Fixed duration
Not effort driven
What I want the MS to do:
The end date should never change
If 2 resources is working 8 hours a day I want the time to be 16 hours, if 1 more joins the project, 24 hours.
I just want the working time per resourse to change, not the time for the project.
HELP!
I have one file for resources and 2 files for projects.
They are connected.
When I updated the resources vacation the end date in the project files changed.
Settings are:
Fixed duration
Not effort driven
What I want the MS to do:
The end date should never change
If 2 resources is working 8 hours a day I want the time to be 16 hours, if 1 more joins the project, 24 hours.
I just want the working time per resourse to change, not the time for the project.
HELP!