pedrosantos
IS-IT--Management
Hi!!!
Imagine that I have a 2h task with two resources assigned and I want resource 1 to work 0,5h at the beginning, resource 2 1h after the inicial resource 1 work and finally another 0,5h of resource 1 at the end. I could do this with three connected tasks each with its own resource. However, I really need to indent those tasks and assign resources to the resulting summary task.
My question is, adding the resources to the summary task and manually editing each resource work, if that summary task turn out to be overlocatted if a levelling is applied will my custom countour remain unchanged?
Thanks to all.
Imagine that I have a 2h task with two resources assigned and I want resource 1 to work 0,5h at the beginning, resource 2 1h after the inicial resource 1 work and finally another 0,5h of resource 1 at the end. I could do this with three connected tasks each with its own resource. However, I really need to indent those tasks and assign resources to the resulting summary task.
My question is, adding the resources to the summary task and manually editing each resource work, if that summary task turn out to be overlocatted if a levelling is applied will my custom countour remain unchanged?
Thanks to all.