Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations strongm on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

View Resource name, Position and days per month

Status
Not open for further replies.

blinton25

Programmer
Mar 20, 2004
104
BB
Hi,

Is it possible to generate a view using Microsoft Project similar to the image shown?
 
I'm not sure what the "5" represents but this looks close to the Resource Usage view zoomed out to show Months over weeks. The additional data could be shown through custom text fields.
 
5 would be the number of days spent by the resource in the week.

How would I define Custom text fields?
 
Add a text field (Text1) to the Resource Usage view and enter the data in the field. You can, if desired, create a lookup list to set a group of values to select from.
 
Thanks, that worked.

As well, how do I change the view from showing hours to show days?
 
In Project 2007: Tools > Options, Schedule.
In Project 2010: File tab, Options, Schedule.

"Work is entered in: Days"
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top