Hello,
After baseline the project i am trying to view the slipping of a certain task here is my question
1- baseline finish date 4/1/2010
1- update task
2- % complete only 25 %
3- current date 4/21/2010
4- Tracking gantt
looking at the 2 bars
Gray the baseline
Red Update bar it shows 25% solid red as progress but
A- the finish date do dot Change
B- the task is not done and do know when
what do i need to do see the task (RED BAR)is slipping to the Right.
Many Thanks

 
Before entering the %WorkComplete figure (in your case, 25%), you must first tell Project when work on the task actually began.

1. View > Gantt
2. Insert the column "Actual Start"
2. Change the date from NA to the date when work actually started.
3. Enter the %WorkComplete number.

You should see the display you were expecting.
 