Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations strongm on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Tracking Progress

Status
Not open for further replies.

VVAC123

Technical User
Nov 27, 2009
17
US
Hello,
After baseline the project i am trying to view the slipping of a certain task here is my question
1- baseline finish date 4/1/2010
1- update task
2- % complete only 25 %
3- current date 4/21/2010
4- Tracking gantt
looking at the 2 bars
Gray the baseline
Red Update bar it shows 25% solid red as progress but
A- the finish date do dot Change
B- the task is not done and do know when
what do i need to do see the task (RED BAR)is slipping to the Right.
Many Thanks

 
Before entering the %WorkComplete figure (in your case, 25%), you must first tell Project when work on the task actually began.

1. View > Gantt
2. Insert the column "Actual Start"
2. Change the date from NA to the date when work actually started.
3. Enter the %WorkComplete number.

You should see the display you were expecting.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top