Track of actual hours

Status
Not open for further replies.

karsh

IS-IT--Management
Aug 5, 2002
137
IN
Hello:
Once i enter the estimated work hours, how do i keep track of actual hours? as when i enter the actual work(hours) it changes the estimated hours.
We dont want to save it as baseline hours.
Thanks

 
Interesting. Why wouldn't you want to baseline the plan? Doing so would allow you to see where you are relative to the original plan for hours. The baseline can be written over or (depending on the version you use) alternate baseline fields could be used to save the baseline.
 
Hello karsh,
I agree with ponderworks about saving a baseline. A baseline is how you think the project will unfold according to your plan. However, when you enter the "Actual" hours worked you are able to see the difference between how you thought the project was going vs how it is actually going. This type of information is the variance and it can help you make decisions on how to adjust your plan.

With regards to Actual Hours worked are you wanting to track the percentage complete with a task or the actual hours that a resource worked on the task?

Please be aware that if a Resource works less than the hours they are scheduled Project will add the outstanding time to the end of the task and perhaps extending the duration.

What method of entering actual hours are you using? This will help me to describe other methods available.

Regards,
Michael
 