StephHansen
Programmer
I want to be able to track how many hours a task is taking. I have the duration set as my estimated hours and actual work showing number of hours put in to this point. I would also like the top most part, to tell me how many hours total have been worked on the project
It is not calculating the Summary Task Info correctly. If I have 2 tasks under a summary task (1 for 4 hours, 1 for 2 hours-actual work) the Summary actual work is displaying as 12 hours, not 6. (See Below)
Task Name Duration % Comp Actual Work
Client GUI Module 12.88 days 31% 64 hrs
Biographical Info 2.63 days 29% 12 hrs _ Design 5 hrs 80% 4 hrs _ Functionality 2 days 13% 2 hrs
What I want to see is actually:
Task Name Duration % Comp Actual Work
Client GUI Module 12.88 days 31% 6 hrs
Biographical Info 2.63 days 29% 6 hrs _ Design 5 hrs 80% 4 hrs _ Functionality 2 days 13% 2 hrs
Any ideas a better way to do it?
Thanks!
Stephanie
It is not calculating the Summary Task Info correctly. If I have 2 tasks under a summary task (1 for 4 hours, 1 for 2 hours-actual work) the Summary actual work is displaying as 12 hours, not 6. (See Below)
Task Name Duration % Comp Actual Work
Client GUI Module 12.88 days 31% 64 hrs
Biographical Info 2.63 days 29% 12 hrs _ Design 5 hrs 80% 4 hrs _ Functionality 2 days 13% 2 hrs
What I want to see is actually:
Task Name Duration % Comp Actual Work
Client GUI Module 12.88 days 31% 6 hrs
Biographical Info 2.63 days 29% 6 hrs _ Design 5 hrs 80% 4 hrs _ Functionality 2 days 13% 2 hrs
Any ideas a better way to do it?
Thanks!
Stephanie