Hi everyone
I'm having a problem with sub task durations not being totalled correctly for two of the tasks I have in my project. For Task 1, it looks like a sub task of Task 2 is being included in the calculation. I can't seem to fix this. The rest of the project is fine. I even started another project file but it did the same thing.
As an example of the problem:
Task 1 40.9
sub a 25.5wks
sub b 8.8wks
sub c 3.3wks
Task 2 40.7
sub a 3.3
sub b 37.4
The durations are fixed and are entered in weeks
If I zero out sub task C, it'll calculate correctly. Has this happened to anyone else before? I'm stumped as to what the problem is.
Any and all help will be appreciated.
thanks
I'm having a problem with sub task durations not being totalled correctly for two of the tasks I have in my project. For Task 1, it looks like a sub task of Task 2 is being included in the calculation. I can't seem to fix this. The rest of the project is fine. I even started another project file but it did the same thing.
As an example of the problem:
Task 1 40.9
sub a 25.5wks
sub b 8.8wks
sub c 3.3wks
Task 2 40.7
sub a 3.3
sub b 37.4
The durations are fixed and are entered in weeks
If I zero out sub task C, it'll calculate correctly. Has this happened to anyone else before? I'm stumped as to what the problem is.
Any and all help will be appreciated.
thanks