Nov 12, 2009 #1 SystronK Technical User Nov 12, 2009 2 US Creating a new project. Created tasks and resources, assigned resources to their tasks. Task Usage sheet show hours. Why did they automatically post??
Creating a new project. Created tasks and resources, assigned resources to their tasks. Task Usage sheet show hours. Why did they automatically post??
Nov 15, 2009 #2 PDQBach IS-IT--Management Sep 26, 2003 1,523 US You have confused "Work" with "Actual Work Upvote 0 Downvote
Nov 16, 2009 Thread starter #3 SystronK Technical User Nov 12, 2009 2 US Nope. The are posting on Actual Work. Upvote 0 Downvote
Nov 16, 2009 #4 PDQBach IS-IT--Management Sep 26, 2003 1,523 US Actual Hours" don't automatically post. Perhaps you updated %Complete or %WorkComplete. Upvote 0 Downvote
Nov 22, 2009 #5 PDQBach IS-IT--Management Sep 26, 2003 1,523 US You will also see this happen if you enter a date in "Actual Finish Upvote 0 Downvote