Creating a new project. Created tasks and resources, assigned resources to their tasks. Task Usage sheet show hours. Why did they automatically post??
 
Actual Hours" don't automatically post. Perhaps you updated %Complete or %WorkComplete.
 
You will also see this happen if you enter a date in "Actual Finish
 