shortie8481

IS-IT--Management
Jul 8, 2009
2
US
There are two resources assigned to the same task in Microsoft Project. When resource A submits hours to the task, the update goes to the Status Manager as expected. When resource B submits hours for the same task the update goes to someone else. Does any know what could cause this? Thanks in advanced.
 
Has anyone seen this issue before? Any help is greatly appreciated.
 