I am very new to Project but cannot seem to figure out how to deal with military time and beginning and ending a task at a particular time during a day.
Specifically, I have a project whicb works on a 24 hour a day basis. The first task begins at noon on a particular day and is budgeted to take 93 hours. The task that follows imediately after the 93 hours is budgeted for 6 days. I am trying to create a baseline using these two tasks.
Any help would be appreciated!