gtrchaser
IS-IT--Management
- May 27, 2009
- 4
Hi,
I have a task that I want to have a fixed duration of say two weeks, May 1st to May 15th. I also have 3 resources that will work on this task for roughly 2 hours each (don't care when) over the two week task duration. So I would like to show the task as two weeks long and the two hour work or effort by the resources.
I've tried several different methods of entering this in Project 2007 but never seem to be able to have it displayed correctly, I get either a task duration of two weeks for all resources or six hours.
I've done some searching on this and seem to have hit a wall, any ideas?
Thanks.
I have a task that I want to have a fixed duration of say two weeks, May 1st to May 15th. I also have 3 resources that will work on this task for roughly 2 hours each (don't care when) over the two week task duration. So I would like to show the task as two weeks long and the two hour work or effort by the resources.
I've tried several different methods of entering this in Project 2007 but never seem to be able to have it displayed correctly, I get either a task duration of two weeks for all resources or six hours.
I've done some searching on this and seem to have hit a wall, any ideas?
Thanks.