I have 2 tasks that have to take the same amount of time equal duration however have different differing amounts of work which are fixed. the tasks are placing concrete forms( a fixed area) and placing rebar (a fixed Tonnage). they both start at the same time and finish at the same time. the concrete formwork will always be longer. I would like to set the duration of the rebar to equal the duration of the formwork but do it automatically. fix the work and then let project tell me what my resource utilization is so that I can look at my manpower requirements.
Is this possible?
Is this possible?