aussie01
Technical User
- May 8, 2008
- 2
I've used MSP 2000-2003 for a number of years, but I have just started using MSP 2007. I am having a difficult time setting the working hours for a "non-standard default" resource to 60 hours per week instead of the standard 40 hrs per week. When I setup a "resource" calendar for 60 hrs per week and select it for the that resource, it changes the durations of all tasks to reflect a 60 hr week. Most are 40 hr weeks and a select few are a 60 hr week.
What am I doing wrong?
What am I doing wrong?