Hi everybody,
I'm new to Tek-Tips and kind of new to Project, however I try to make question as clear as possible.
So basically the problem I have is related to a project template we use. To each task a relevant team or person is ordered as a resource.
What I would like to create is a schedule deviation for each resource.
I got as far that I have to use baseline, but I could only visualize the total creep. Is there a way group the delays according to values in a column? ie. in my case according to column teams?
Thank you very much for your help!
I'm new to Tek-Tips and kind of new to Project, however I try to make question as clear as possible.
So basically the problem I have is related to a project template we use. To each task a relevant team or person is ordered as a resource.
What I would like to create is a schedule deviation for each resource.
I got as far that I have to use baseline, but I could only visualize the total creep. Is there a way group the delays according to values in a column? ie. in my case according to column teams?
Thank you very much for your help!