Hi, people.
I need to schedule Crystal report 11 based on Oracle 9 procedure quarterly(has to be sent by e-mail from enterprise 1st day of each quarter).
In Schedule tab I see On Demand, Once, Daily...but no Quarter.
I'll appreciate any answer.
Thank you,
Lana
Hi,
This is the correct forum for your question ( I answered the other one as well)
There is an option in the CMC for creating custom calendars which may allow the setting of quarterly dates..Check the Docs ( the Admin guide has details)
To Paraphrase:"The Help you get is proportional to the Help you give.."
Choose the 'Monthly' option, then click the drop-down arrow where the Run option currently says 'on the nth day of the month' - this will give some more options, one of which is 'every n months'.
Choose N = 3, then set the first run to be on the 1st of the next month.