Programmer
I have created a resource (me).
I have created 3 tasks.
Task 1 = Design Page
Task 2 = Build Page
Task 3 = promote page
Task 2 is dependent on task 1 - it can start once task 1 is complete
task 3 is completely independent
I have allocated durations of 1 day each. I have allocated all tasks to the same resource.
On the gant chart task 2 occurs after task 1
However task 3 occurs at the same time as task 1
But it is the same resource working on both tasks.
How do I tell microsoft project that a resource can only work on one task at once???
I'm really stuck!
I have created 3 tasks.
Task 1 = Design Page
Task 2 = Build Page
Task 3 = promote page
Task 2 is dependent on task 1 - it can start once task 1 is complete
task 3 is completely independent
I have allocated durations of 1 day each. I have allocated all tasks to the same resource.
On the gant chart task 2 occurs after task 1
However task 3 occurs at the same time as task 1
But it is the same resource working on both tasks.
How do I tell microsoft project that a resource can only work on one task at once???
I'm really stuck!