Hi - I have a resource pool that I am using to share resources across many projects. However, I had assigned resources to some tasks in a project that I have since deleted because it was unnecessary. My resource pool is now showing these resources overallocated due to the tasks still assigned from the deleted project. Leveling did not work because it noted the resources were too overallocated. It will not let me delete the tasks in the pool and tells me to adjust the tasks in the original project (which is no longer an available file). I also tried deleting the resources in the pool to set them up again and start over, but that did not work either. Please help!