Hi All,
When I update a task (duration extends for example) I am expecting it to change the date of its successor, which is a normal FS link, no restraints & no other predecessors. However it doesn't change unless I save, close & reopen! I remember there being a 'refresh/recalculate' button on my keyboard - but can't remember what it was!
PLEASE HELP!!
Thanks,
DG
When I update a task (duration extends for example) I am expecting it to change the date of its successor, which is a normal FS link, no restraints & no other predecessors. However it doesn't change unless I save, close & reopen! I remember there being a 'refresh/recalculate' button on my keyboard - but can't remember what it was!