Recalculating the plan

Status
Not open for further replies.

DG17

IS-IT--Management
Nov 8, 2010
7
GB
Hi All,

When I update a task (duration extends for example) I am expecting it to change the date of its successor, which is a normal FS link, no restraints & no other predecessors. However it doesn't change unless I save, close & reopen! I remember there being a 'refresh/recalculate' button on my keyboard - but can't remember what it was!

PLEASE HELP!!

Thanks,
DG
 
check your calculation setting. go to Tools, Options, Calculation and make sure the setting is Automatic
or
press F9

gem1941
 
Gem - You're a star!! THANKS! :)
 