I'm trying to get access to project future dates from the date i initially enter. For example, If I entered 6 Jan 2002, I would want one field to project out 3 months, another 6 months, and the third one year.
Hi Sentra52,
Using Access 2000:
In the after update event of the date your are entering, set the other date fields using the DateAdd function.
Example:
Private Sub Action_Date_AfterUpdate()
newdate= DateAdd("m", 3, Action_Date)
End Sub
The above example sets date field newdate to value of Action_Date plus 3 months.