Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations strongm on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

project: priority field

Status
Not open for further replies.

althea

MIS
Oct 15, 2001
134
US
I can't figure out what the 'priority' field does. It appears in the Project Information box and also in 'task information' box. Anyone ever changed the default of 500 to something else for a particular reason?
Thanks,
 
It has to do with leveling resources. Search on Priority or 'About Resource Leveling' in the help for more information. (I'm using Project Pro 2003, but I would think the same searches would work in other versions.)
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top