Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations Chris Miller on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Project allocates times in reverse? Newbie

Status
Not open for further replies.

iXPhound

Technical User
Feb 25, 2001
146
US
Hi all:

I apologize for what may very well be my own ignorance. I am new to MS Project 2002 and I am having a problem, so I hope someone can help. I have a task that starts on 11/28 and ends 11/29. The duration of this task is 14hrs. Why does project assign the 6 hours of work time on 11/28 and 8 hours on 11/29...shouldn't it be the reverse? How do I change this? Thanks in advance!!
 
Look under Task Info, Advanced Tab, is your constraint "as late as possible" rather than defaulting to "as soon as possible"?
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top