gjones1234
Technical User
I've been using MS Project 2003 for several months. Pretty basic usage - linked tasks, general ghantt chart.
All of a sudden, as of just now, when I change the date for a task, none of the dates in the linked tasks change.
Is there a setting or something else that I have inadvertantly changed? I am using duration, start, and finish fields. The link is FS with 0 lag time.
Please help ASAP. Thanks!
All of a sudden, as of just now, when I change the date for a task, none of the dates in the linked tasks change.
Is there a setting or something else that I have inadvertantly changed? I am using duration, start, and finish fields. The link is FS with 0 lag time.
Please help ASAP. Thanks!