I am using Project 2000, however I have had this situation occur in earlier versions of product...
1. The task splits itself on the Gantt chart; I try to drag it back to rejoin the original section of the task and it won't budge. Constraint is set to ASAP. No changes to the calendar or working time that should prevent the task from being able to be worked those days. The split is approximately 2 weeks... I have actual work posted on Mon & Tues of the beginning of the task, and then it jumps 2 weeks into the future for the remaining work. Any ideas how to get the work back into the original week?
2. This is related to problem #1. In the Resource Usage view, I cleared the remaining work "out in the future" of that task. I then, on Wednesday of the week I really want the work to appear, I entered 2 hours into Work. That 2 hours immediately jumped 2 weeks into the future... and split into 1.25 hours on Monday & .75 on Tuesday! Again, I have normal 8 hour days set up, with no modifications to the calendar.
Has anyone experienced this before? How do you go about fixing it? Is there a setting I'm missing somewhere?
Thank you!
Janice
1. The task splits itself on the Gantt chart; I try to drag it back to rejoin the original section of the task and it won't budge. Constraint is set to ASAP. No changes to the calendar or working time that should prevent the task from being able to be worked those days. The split is approximately 2 weeks... I have actual work posted on Mon & Tues of the beginning of the task, and then it jumps 2 weeks into the future for the remaining work. Any ideas how to get the work back into the original week?
2. This is related to problem #1. In the Resource Usage view, I cleared the remaining work "out in the future" of that task. I then, on Wednesday of the week I really want the work to appear, I entered 2 hours into Work. That 2 hours immediately jumped 2 weeks into the future... and split into 1.25 hours on Monday & .75 on Tuesday! Again, I have normal 8 hour days set up, with no modifications to the calendar.
Has anyone experienced this before? How do you go about fixing it? Is there a setting I'm missing somewhere?
Thank you!
Janice