Dear all
I ran into a weird situation with MS-Project 2010,
I entered a task in the Gantt View. I added resources, the usage of their utilization etc.
The task is based on units.
When I use the resoure usage view, I suddenly see the task below the ressource mentioned four times and the hours are aggegated which gives me a wrong number of hours this person worked or is planned to work.
I couldn't figure out how this can happen.
Any idea or things to look at?
Thanks in advance.
bumpui