I am trying to use Project as more of an indicator of Resources workload across many projects rather than actual Project Management.
Therefore I have the following configuration:
- 6 tasks in each project
- Tasks are manually scheduled and all linked
- Tasks are using a 24 hour calendar
- Tasks area all Fixed Duration
- My resources are stored in a pool file and all use the Standard calendar
- I am applying resource work hours to each task but the hours of work are far shorter than the task duration. i.e. 85hrs work against a 79 day task.
The problem I am seeing is when I add or change resource hours then project is changing the task duration. I thought the Fixed Duration task type would prevent this?
Can anybody let me know what I am doing wrong or whether my configuration is correct or not?
Thanks
Therefore I have the following configuration:
- 6 tasks in each project
- Tasks are manually scheduled and all linked
- Tasks are using a 24 hour calendar
- Tasks area all Fixed Duration
- My resources are stored in a pool file and all use the Standard calendar
- I am applying resource work hours to each task but the hours of work are far shorter than the task duration. i.e. 85hrs work against a 79 day task.
The problem I am seeing is when I add or change resource hours then project is changing the task duration. I thought the Fixed Duration task type would prevent this?
Can anybody let me know what I am doing wrong or whether my configuration is correct or not?
Thanks