AntzyClancy
Technical User
This is a little complicated. Let’s say I have 5 or so separate installation activities that each require the same WAP approval. Each of the these 5 activities have completion dates that move around a lot. I’d like the WAP done 10 days before the earliest of these 5 activities. How do I tie these together?
The way I’ve done this in the past is to add a predecessor to the WAP task with a “SF-10day” qualifier. Trouble is that this only works with a single activity, which requires me to constantly evaluate all of the activities to determine which is the first to start. If I use the same qualifier on multiple activities in the WAP task predecessor field, the WAP due date becomes driven by the latest activity, not the earliest.
The way I’ve done this in the past is to add a predecessor to the WAP task with a “SF-10day” qualifier. Trouble is that this only works with a single activity, which requires me to constantly evaluate all of the activities to determine which is the first to start. If I use the same qualifier on multiple activities in the WAP task predecessor field, the WAP due date becomes driven by the latest activity, not the earliest.