I have run into a situation where the user has reduced the Expect cost of an item in order to break it out onto a another line. The change shows correctly on the Purchase Order but I found that at the time of receiving the Unit Cost still shows as the original amount.
Looking at the Line and Line Audit tables I see that the Act_unit_cost did not get updated and I am assuming that is the field that the Receiver report is pulling the Unit cost value from.
Is the by design, user error or a bug?
Any ideas?
Jake
Looking at the Line and Line Audit tables I see that the Act_unit_cost did not get updated and I am assuming that is the field that the Receiver report is pulling the Unit cost value from.
Is the by design, user error or a bug?
Any ideas?